Project Name

Especial Way of Golestan Forest

Main Technical Features

Length 22 km
Width 11.00 m
Retaining Wall ---
No. of Slab/Arc Culverts 73
No. of Bridges 10 x 45 meters lenght
Earth works 1,650,000 m3

Location

Golestan Province

Employer

Ministry of Road & Transportation

Date of Award

March 2005

Position

In progress (5% completed)

App. Cost of Project

262,000 (Million Rials)

 