Project Name |
Especial Way of Golestan
Forest |
|
Main
Technical Features |
Length |
22 km |
|
Width |
11.00 m |
|
Retaining Wall |
--- |
|
No. of Slab/Arc Culverts |
73 |
|
No. of Bridges |
10 x 45 meters lenght |
|
Earth works |
1,650,000 m3 |
|
Location |
Golestan Province |
|
Employer |
Ministry of Road & Transportation |
|
Date of
Award |
March 2005 |
|
Position |
In progress (5% completed) |
|
App. Cost of
Project |
262,000 (Million Rials) |
  
|
|